I'm installing a PQube 3 using two PTs and two CTs. How do I wire this? Do I need a special configuration?

On the PQube 3, connect phase A to the L1 terminal, phase B (tied to earth) to the L2 terminal, and phase C to the L3 terminal. In the PQube 3’s Setup.ini file, set the “power configuration” = Delta and “calculate remaining current channel” = L2. This assumes you have a CT on phase A and phase C. Use the PQube 3 Configurator program, <insert link to download> to edit your Setup.ini file.